Do specifications supersede drawings?
If there is a conflict between the Drawings and Details on Drawings and the Specifications, then the Specifications will prevail
. The higher “Order of Precedence of Documents” governs or prevails.
Do specifications govern over drawings?
In case of difference between drawings and specifications, the specifications shall govern
. In case of discrepancy in the figures, in the drawings, or in the specifications, the matter shall be promptly submitted to the Contracting Officer, who shall promptly make a determination in writing.
Do construction drawings or specifications take precedence?
Supplement 5252.236-9312, Design Build Contract-Order of Precedence, which showed that
specifications took precedence over concept drawings
. General requirements, which stated “in case of differences between project specifications and the accompanying drawings, the specifications will govern.”
Are the specifications the same as drawings?
What is the order of precedence for construction documents?
5 ORDER OF PRECEDENCE In case of any inconsistency, conflict, or ambiguity among the Contract Documents, the documents shall govern in the following order:
(a) Change Orders and written amendments to this Agreement; (b) this Agreement; (c) subject to subsection 14.2
.
Are drawings part of the specification?
The project drawings and specifications are an integral part of the contract documents and are inseparable
. The drawings reflect what the project specifications are unlikely to cover; and the project specifications indicate what the drawings are unlikely to portray.
What is the relationship between the working drawings and the specifications?
An over-simplified but general rule of thumb is
drawings reflect the scope of a design while specifications describe its quality
.
What is the difference between plans and specifications?
Your house plans are a set of scaled drawings that show contractors what they are building. Your specifications (or specs) are a written document that details what materials will be used and how to install things.
Do shop drawings supersede architectural drawings?
As long as there is conformity between the shop drawings and the contract documents, the architect’s approval indicates that the architect approves of the contractor’s interpretation of the contract requirements. In the event that there is a subsequent dispute, that approval is binding on the architect or owner.
Which takes precedence in a contract?
In the event of a conflict between or among the Contract documents, the order of precedence shall be
the provisions of the main body of this Contract
, i.e., those provisions set forth in the recitals and articles of this Contract, and then the exhibits and attachments.
How are specifications used in construction drawings?
Construction specifications, or specs,
detail the work and workmanship required for each construction project
. A specs definition is “written documentation describing the scope of work, any materials that are to be used, the methods of installation, and the quality of workmanship under contract.”
What is the purpose of construction specifications?
It
provides an understanding of the performance requirements of the whole project
, so that when discussions develop on complexes, entities, space, locations, elements, systems and products, these form part of the build-up of a specification.
What is included in plans and specifications?
Plans and Specifications means
plans, drawings, specifications and other documents from which the Buildings, Ancillary Buildings, Garages and Landscaping are to be constructed
(including details of materials, colours, location and design).
What written document has priority over the specifications book?
The
general provisions document
takes precedence over both the special provisions document and the contract when the terms of the three documents have different conditions or language that causes confusion.
What takes precedence employer’s requirements or contractor’s proposals?
The employer is responsible for the design in the Employer’s Requirements
. The contractor is responsible for completing that design. Unfortunately, the reality is often different because of what the parties attach as the Employer’s Requirements and the Contractor’s Proposals.
What is an order of precedence describe it?
An order of precedence is
a sequential hierarchy of nominal importance
and can be applied to individuals, groups, or organizations. Most often it is used in the context of people by many organizations and governments, for very formal and state occasions, especially where diplomats are present.
What are drawings and specifications?
Construction Drawings and Specifications means the final working drawings and specifications for the Work, issued by Engineer and describing the size, character, design, construction, materials, finishes, and structural, mechanical, electrical and other systems of the Project.
Does Bill of Quantities take precedence over specification?
If the contract is with quantities, the BoQ as prepared by the Employer takes precedence over the drawings and specification
. Any missing items from the BoQ are dealt with as a change and therefore a client risk.
What are the 4 types of specifications?
Why do we need to follow or implement the standards and specifications in engineering drawings?
The specification
provides clear instructions on project intent, performance and construction
. It can reference the quality and standards which should be applied. Materials and manufacturers’ products can be clearly defined. Installation, testing and handover requirements can be identified.
What are seven types of specifications that may be included in a drawing plan?
When writing project documents, you should follow the seven C’s:
clear, concise, correct, complete, comprehensive, consistent, co-ordinated
. These apply not only for textual documents, but also for information provided directly on drawings and schedules.
What is the difference between working drawings and construction drawings?
Construction Drawings are Architectural Construction Documents (CD set) also known as working drawings are prepared to envision the architectural elements in the building or the building before construction starts
.
What is the difference between construction drawings and specifications?
What is the difference between drawings and plans?
Unsourced material may be challenged and removed.
Plans are a set of drawings or two-dimensional diagrams used to describe a place or object, or to communicate building or fabrication instructions
. Usually plans are drawn or printed on paper, but they can take the form of a digital file.
What is the difference between design build and plan and spec?
In plan and spec, the owner has a design ready, the contractor’s job is to carry it out. In design-build, however, the contractor oversees design and construction
. The owner gives room for contractors to bid on the design and can calculate how much the project will cost in anticipation of what contractors will bid.
Do architects review shop drawings?
7: The Architect will review and approve or take other appropriate action upon the Contractor’s submittals such as Shop Drawings, Product Data and Sam- ples, but only for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract documents.
What is the difference between shop drawings and as-built drawings?
The as-built drawings are made after the completion of the project. And the shop drawings are made before a construction project starts
.
Does the architect need to approve the sub contractor’s shop drawings?
The architect will rarely have any obligation to approve a sub-contractor’s shop drawings unless the sub-contractor has a design obligation or the contract documents expressly require the architect to approve such drawings.
Which takes precedence contract or purchase order?
When there is a conflict in terms on a contract there is a precedence that applies?
Do special conditions take precedence over general conditions?
In the event of conflict or inconsistency between the provisions of the Australian Standard General conditions of contract (AS2124-1992) and the Special Conditions of Contract,
the Special Conditions of Contract shall take precedence
.
What are the 3 types of construction specifications?
How important is specifications in a construction project?
A primary function of project specifications is
to deliver detailed information regarding materials and methods of work for a particular construction project
. They cover various components relating to the project, including general conditions, scope of work, quality of materials, and standards of workmanship.
Why is specification needed and its importance?
Specifications are made
to explain the formation, type, building methodology and strength of the constructional work to represent its quality
, i.e., constructional work. These are information which can not be explained through drawings.
What is difference between specification and requirement?
Q. What is the difference between a “requirement” and a “specification”? The dictionary tells us that
a requirement is something that is needed and that a specification is a precise description of an item
.
Does Bill of Quantities take precedence over specification?
If the contract is with quantities,
the BoQ as prepared by the Employer takes precedence over the drawings and specification
.