When Must An Assured Equipment Grounding Conductor Program Be In Place?

When Must An Assured Equipment Grounding Conductor Program Be In Place? Before first use. After any repairs, and before placing back in service. After suspected damage, and before returning to use. Every 3 months [for exceptions see, 29 CFR 1926.404(b)(1)(iii)(E)(4)]. What is an assured equipment grounding conductor program? Assured Equipment Grounding Conductor Program (AEGCP) is

What Is The Minimum Standard Approved Grounding Wire Size?

What Is The Minimum Standard Approved Grounding Wire Size? Section 250.52(A)(4) requires that the minimum size conductor and material for a ground ring is 2 AWG copper. What gauge should ground wire be? If enough ground fault current flows, the circuit breaker will trip. Even without AFCI breakers, the 16-gauge ground wire should be adequate