Which Activity Can You Delay By One Day Without Impacting The Expected Completion Date For The Project?

Which Activity Can You Delay By One Day Without Impacting The Expected Completion Date For The Project? Float, sometimes called slack, is the amount of time an activity, network path, or project can be delayed from the early start without changing the completion date of the project. Total float is the difference between the finish